A software company needs to develop a project that is estimated as 1000 function points and is planning to use JAVA as the programming language whose approximate lines of code per function point is accepted as 50. Considering a = 1.4 as multiplicative factor, b = 1.0 as exponential factor for the basic COCOMO effort equation and c = 3.0 as multiplicative factor, d = 0.33 as exponential factor for the basic COCOMO duration equation, approximately how long does the project take to complete?
(A)
11.2 months
(B)
12.2 months
(C)
13.2 months
(D)
10.2 months
Answer
Please comment below if you find anything wrong in the above post
Feeling lost in the world of random DSA topics, wasting time without progress? It's time for a change! Join our DSA course, where we'll guide you on an exciting journey to master DSA efficiently and on schedule.
Ready to dive in? Explore our Free Demo Content and join our DSA course, trusted by over 100,000 geeks!